h2integrate.simulation.technologies.hydrogen.electrolysis.H2_cost_model

h2integrate.simulation.technologies.hydrogen.electrolysis.H2_cost_model#

Functions

basic_H2_cost_model(electrolyzer_capex_kw, ...)

Basic cost modeling for a PEM electrolyzer.

h2integrate.simulation.technologies.hydrogen.electrolysis.H2_cost_model.basic_H2_cost_model(electrolyzer_capex_kw, time_between_replacement, electrolyzer_size_mw, useful_life, atb_year, electrical_generation_timeseries_kw, hydrogen_annual_output, PTC_USD_kg, ITC_perc, include_refurb_in_opex=False, offshore=0)#

Basic cost modeling for a PEM electrolyzer. Looking at cost projections for PEM electrolyzers over years 2022, 2025, 2030, 2035. Electricity costs are calculated outside of hydrogen cost model

Needs: Scaling factor for off-shore electrolysis Verifying numbers are appropriate for simplified cash flows Verify how H2 PTC works/factors into cash flows

If offshore = 1, then additional cost scaling is added to account for added difficulties for offshore installation, offshore=0 means onshore